Xcel Seeks Colorado Supreme Court Ruling to Connect Wind Farms
Xcel’s Colorado unit asks the state Supreme Court to address an eminent-domain fight that has blocked easement access for gen-tie lines to two almost-complete wind projects totaling over 1 GW. A district judge rejected PSCo’s bid, delaying grid interconnection and renewable deliveries while raising costs, as appeals could take more than a year.