Oracle Shares Fall After Pipeline Delay for New Mexico AI Data Center
Transwestern Pipeline, a unit of Energy Transfer, told federal regulators that the Green Chile gas pipeline’s target completion moved to February 1, 2027, from August 15, 2026, after permitting setbacks. The delay showed up in a regulatory filing tied to the pipeline planned to power Oracle’s Project Jupiter AI data center in Doña Ana County, and Oracle shares fell as much as 5%.