Judge Denies Bid to Block Arkansas Media from Google Energy Docs
An Arkansas federal judge denied Entergy Arkansas’s request for a temporary restraining order to stop the Arkansas Democrat-Gazette and other defendants from publishing additional details from confidential documents. The documents describe the company’s role in building the Cypress Solar project—a 600-megawatt solar and 350-megawatt battery facility supplying power for Google’s West Memphis data center—highlighting a $526 million payment tied to the project’s roughly $1.6 billion price tag.