Green Chile Gas Pipeline for Oracle AI Data Center Delayed to 2027
A key New Mexico gas pipeline planned to fuel a planned Oracle AI data center is delayed, with an estimated in-service date pushed to Feb. 1, 2027 from an earlier Aug. 15 target. Project Jupiter remains on schedule, but Green Chile is not expected to enter service until at least late 2027 and could face cancellation. The 400 million cubic feet per day project is tied to up to $165 billion in investment for Doña Ana County amid state and federal certification obstacles.